SEASONS RESIDENCE NEWSLETTER, JUNE 2009
HOME  |  NEWS  |  CONSTRUCTION

WWW.SEASONS.RO
Buildings 2, 3 and 4 are under continuous structuring works. In building 5, the works advanced to the interior and with the finishings. Building 6 rose up to the sixth level and it is only 2 floors away from completing the structure, which is estimated for the beginning of July. The construction works advanced also in building 7, which is at the fifth level and will reach red stage at the middle of August.